Saturday, November 21, 2009

Land speed record---All serves in (drum roll please..) 2:30

Overall: [ Ahead of schedule ]

Status notes: All servers in racks at 2:30. Incredible team effort. No accidents, no injuries, no problem........ Finalizing patching.

San up and operational. All discs operational, checked, good.........YAHOOOOOOOOOOO

Delays: None

Next Update: 5:00 am

Old Data Center EMPTY -- 1:07

Overall: [ Ahead of Schedule ]

Status notes: WOW!! The un-rack team ROCKS!!! Hours ahead of schedule - not drops, no owies, no foul

Delays: None

Next Update: 3:00 am

Friday, November 20, 2009

Overall: [ Ahead of Schedule - slightly ]

Status notes: Servers all down, move in progress. Have all chasis in new Data Center and racking starting. San is coming out of Rack. Moving switch.

Only issue to report is door alarms in new DC ringing again.......unplugged to stop from ringing. Will work with Don Borden to remedy

Delays: None

Next Update: 3:00 am

Shut-Down Status - 8:30 Friday

Overall: [ Ahead of schedule ]

Status notes: C & D applications down, B on the way. Should be completed by 9:15.

Delays: None

Next Update: 10:00 pm

The Move is ON!!

Overall: [ On schedule ]

Status notes: Things are ready. 


Delays: None to speak of.


Next Update: 8:30 PM

Tuesday, November 17, 2009

Sample Post Template

Overall: [ On schedule / Behind by x min / stopped - major issue / go back ]

Status notes:
  special team instructions (bring donuts, show up at 10 instead of 9)
  use the NE door instead of the SW door
  Check in with Tamra - Ader is sick

Delays:


Next Update: 3:00am