Overall: [ Ahead of Schedule - slightly ]
Status notes: Servers all down, move in progress. Have all chasis in new Data Center and racking starting. San is coming out of Rack. Moving switch.
Only issue to report is door alarms in new DC ringing again.......unplugged to stop from ringing. Will work with Don Borden to remedy
Delays: None
Next Update: 3:00 am
Friday, November 20, 2009
Shut-Down Status - 8:30 Friday
Overall: [ Ahead of schedule ]
Status notes: C & D applications down, B on the way. Should be completed by 9:15.
Delays: None
Next Update: 10:00 pm
Status notes: C & D applications down, B on the way. Should be completed by 9:15.
Delays: None
Next Update: 10:00 pm
The Move is ON!!
Overall: [ On schedule ]
Status notes: Things are ready.
Delays: None to speak of.
Next Update: 8:30 PM
Status notes: Things are ready.
Delays: None to speak of.
Next Update: 8:30 PM
Tuesday, November 17, 2009
Sample Post Template
Overall: [ On schedule / Behind by x min / stopped - major issue / go back ]
Status notes:
special team instructions (bring donuts, show up at 10 instead of 9)
use the NE door instead of the SW door
Check in with Tamra - Ader is sick
Delays:
Next Update: 3:00am
Status notes:
special team instructions (bring donuts, show up at 10 instead of 9)
use the NE door instead of the SW door
Check in with Tamra - Ader is sick
Delays:
Next Update: 3:00am